|
|
|
Rockefeller
Hall Renovation — Updates
Construction Progress Report (October 2007)
Interior construction is tracking on schedule. All base abatement and
demolition work has been completed. Interior framing and rough installation of
mechanical, electrical, plumbing, and fire protection systems is underway on all
floors. Rough-in is substantially complete on floors 2 through 4. Underpinning
is complete at the new elevator pit, and the elevator shaft openings have been
cut on each floor. New structural steel work is complete, as are miscellaneous
metal clips and supports.
On the exterior work, the new roof installation will start in early
November. Brick-staining work is approximately 75 percent complete.
Site preparation work is substantially complete within the fenced-in site,
including removal of trees, paving, and site improvements. In addition, on
October 24, the site fence was reconfigured to include the limit of
work at the southern end of the site, along the west side of Andover-Harvard
Theological
Library. A new temporary pedestrian path was provided for access to Andover Hall
and the library, and a new bike rack location was established. This will allow
for completion of the balance of the pavement removal and solids replacement.
Project Focus: Sustainability
An important goal of the Rockefeller project is to reestablish Rockefeller
Hall as a sustainable building. As a result, numerous design and energy
conservation measures are being implemented, as described in the following
documents:
Sustainability Plan (June 15, 2007)
The Rockefeller Hall reconstruction project also includes efforts toward
sustainability through reuse and recycling. The first stage in the recycling
plan was the reuse of all loose furniture and equipment, which was initially
offered to the HDS community in June 2007; furniture not taken by HDS employees
and students was donated to the general public. The second step is the removal
of kitchen equipment, doors, light fixtures, and plumbing fixtures for reuse in
third world countries. This work is coordinated through the
Institutional Recycling Network, a
nonprofit with connections to NGOs (nongovernmental organizations) throughout
the world. These items will be warehoused in the Caribbean until donated.
Finally, during construction, demolition items will be separated for recycling
into dumpsters for masonry, different metals, and drywall. Early estimates by
Harvard Green Campus have our
recycling efforts projected at 95 percent of the building.
|